Q66.
Maya does 60% of a work in 18 days. She then calls Puja and both together finish the rest of the work in 6 days. How many days would Puja alone take to complete the work?
Asked in 27 October 2026 Shift 2 (01:30 PM - 02:30 PM).
Maya does 60% of a work in 18 days. She then calls Puja and both together finish the rest of the work in 6 days. How many days would Puja alone take to complete the work?