Q75.
A contractor hires 10 workers who can complete a task in 16 days. After 4 days, he fires 2 workers. How many more days will the remaining workers take to complete the task?
Asked in 26 September 2025 Shift 2 (11:45 AM - 12:45 PM).
A contractor hires 10 workers who can complete a task in 16 days. After 4 days, he fires 2 workers. How many more days will the remaining workers take to complete the task?