Q62.
40 men can complete a work in 30 days. However, if 10 men leave the group, how many days will the group take to complete the work?
Asked in 27 July 2023 Shift 3 (02:30 PM - 03:30 PM).
40 men can complete a work in 30 days. However, if 10 men leave the group, how many days will the group take to complete the work?